Engineering Evaluation of parallel construction for Shield Tunnel and connecting channels-case study of Taipei MRT tunnel Project.
碩士 === 國立臺灣海洋大學 === 河海工程學系 === 106 === Normally, MRT of corss passageare section will be completing after finished shield tunnel/ invert/walkway. Often facing: (1) It requires plenty of manpower and longer lead time, difficult to improve execution rate. (2) During Shielding and corss passageare con...