Application of Grouting Method for Underground Excavation Construction of Urban Rail Transit Connecting Passage in Water-rich Sandy Cobble Stratum
Objective Connecting Passage 1 in the interval of Jiujiang North Station and Longqiao Road Station of Chengdu Metro Line 19 Phase II is located in water-rich sandy cobble stratum. Limited by the location of the surrounding buildings (structures), it is not suitable to adopt conventional method for t...
| الحاوية / القاعدة: | Chengshi guidao jiaotong yanjiu |
|---|---|
| المؤلفون الرئيسيون: | , , , , |
| التنسيق: | مقال |
| اللغة: | الصينية |
| منشور في: |
Urban Mass Transit Magazine Press
2024-08-01
|
| الموضوعات: | |
| الوصول للمادة أونلاين: | https://umt1998.tongji.edu.cn/journal/paper/doi/10.16037/j.1007-869x.2024.08.059.html |