Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts Devices

The use of renewable energy such as wind power is one of the most affordable solutions to meet the basic demand for electricity because it is the cleanest and most efficient resource. In Algeria, the highland region has considerable wind potential. However, the electrical power system located is thi...

Full description

Bibliographic Details
Published in:Applied Sciences
Main Authors: Lina Wang, Kamel Djamel Eddine Kerrouche, Abdelkader Mezouar, Alex Van Den Bossche, Azzedine Draou, Larbi Boumediene
Format: Article
Language:English
Published: MDPI AG 2018-11-01
Subjects:
Online Access:https://www.mdpi.com/2076-3417/8/11/2250
_version_ 1856908118491922432
author Lina Wang
Kamel Djamel Eddine Kerrouche
Abdelkader Mezouar
Alex Van Den Bossche
Azzedine Draou
Larbi Boumediene
author_facet Lina Wang
Kamel Djamel Eddine Kerrouche
Abdelkader Mezouar
Alex Van Den Bossche
Azzedine Draou
Larbi Boumediene
author_sort Lina Wang
collection DOAJ
container_title Applied Sciences
description The use of renewable energy such as wind power is one of the most affordable solutions to meet the basic demand for electricity because it is the cleanest and most efficient resource. In Algeria, the highland region has considerable wind potential. However, the electrical power system located is this region is generally not powerful enough to solve the problems of voltage instability during grid fault conditions. These problems can make the connection with the eventual installation of a wind farm very difficult and inefficient. Therefore, a wind farm project in this region may require dynamic compensation devices, such as a distributed-flexible AC transmission system (D-FACTS) to improve its fault ride through (FRT) capability. This paper investigates the implementation of shunt D-FACTS, under grid fault conditions, considering the grid requirements over FRT performance and the voltage stability issue for a wind farm connected to the distribution network in the Algerian highland region. Two types of D-FACTSs considered in this paper are the distribution static VAr compensator (D-SVC) and the distribution static synchronous compensator (D-STATCOM). Some simulation results show a comparative study between the D-SVC and D-STATCOM devices connected at the point of common coupling (PCC) to support a wind farm based on a doubly fed induction generator (DFIG) under grid fault conditions. Finally, an appropriate solution to this problem is presented by sizing and giving the suitable choice of D-FACTS, while offering a feasibility study of this wind farm project by economic analysis.
format Article
id doaj-art-fac94de7f6344ab28d27c76ca258c278
institution Directory of Open Access Journals
issn 2076-3417
language English
publishDate 2018-11-01
publisher MDPI AG
record_format Article
spelling doaj-art-fac94de7f6344ab28d27c76ca258c2782025-08-19T20:21:39ZengMDPI AGApplied Sciences2076-34172018-11-01811225010.3390/app8112250app8112250Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts DevicesLina Wang0Kamel Djamel Eddine Kerrouche1Abdelkader Mezouar2Alex Van Den Bossche3Azzedine Draou4Larbi Boumediene5School of Automation on Science and Electrical Engineering, Beihang University, Beijing 100191, ChinaSchool of Automation on Science and Electrical Engineering, Beihang University, Beijing 100191, ChinaElectro-Technical Engineering Lab, Faculty of Technology, Tahar Moulay University, Saida 20 000, AlgeriaElectrical Energy LAB EELAB Sint–Pietersnieuwstraat 41, B 9000 Ghent, BelgiumDepartment of Electrical Engineering, Madinah Mounawara University, Madinah 20012, Saudi ArabiaElectro-Technical Engineering Lab, Faculty of Technology, Tahar Moulay University, Saida 20 000, AlgeriaThe use of renewable energy such as wind power is one of the most affordable solutions to meet the basic demand for electricity because it is the cleanest and most efficient resource. In Algeria, the highland region has considerable wind potential. However, the electrical power system located is this region is generally not powerful enough to solve the problems of voltage instability during grid fault conditions. These problems can make the connection with the eventual installation of a wind farm very difficult and inefficient. Therefore, a wind farm project in this region may require dynamic compensation devices, such as a distributed-flexible AC transmission system (D-FACTS) to improve its fault ride through (FRT) capability. This paper investigates the implementation of shunt D-FACTS, under grid fault conditions, considering the grid requirements over FRT performance and the voltage stability issue for a wind farm connected to the distribution network in the Algerian highland region. Two types of D-FACTSs considered in this paper are the distribution static VAr compensator (D-SVC) and the distribution static synchronous compensator (D-STATCOM). Some simulation results show a comparative study between the D-SVC and D-STATCOM devices connected at the point of common coupling (PCC) to support a wind farm based on a doubly fed induction generator (DFIG) under grid fault conditions. Finally, an appropriate solution to this problem is presented by sizing and giving the suitable choice of D-FACTS, while offering a feasibility study of this wind farm project by economic analysis.https://www.mdpi.com/2076-3417/8/11/2250wind farmFault Ride Through (FRT)Distributed-Flexible AC Transmission system (D-FACTS)Distribution Static VAr Compensator(D-SVC)Distribution Static Synchronous Compensator (D-STATCOM)
spellingShingle Lina Wang
Kamel Djamel Eddine Kerrouche
Abdelkader Mezouar
Alex Van Den Bossche
Azzedine Draou
Larbi Boumediene
Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts Devices
wind farm
Fault Ride Through (FRT)
Distributed-Flexible AC Transmission system (D-FACTS)
Distribution Static VAr Compensator(D-SVC)
Distribution Static Synchronous Compensator (D-STATCOM)
title Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts Devices
title_full Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts Devices
title_fullStr Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts Devices
title_full_unstemmed Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts Devices
title_short Feasibility Study of Wind Farm Grid-Connected Project in Algeria under Grid Fault Conditions Using D-Facts Devices
title_sort feasibility study of wind farm grid connected project in algeria under grid fault conditions using d facts devices
topic wind farm
Fault Ride Through (FRT)
Distributed-Flexible AC Transmission system (D-FACTS)
Distribution Static VAr Compensator(D-SVC)
Distribution Static Synchronous Compensator (D-STATCOM)
url https://www.mdpi.com/2076-3417/8/11/2250
work_keys_str_mv AT linawang feasibilitystudyofwindfarmgridconnectedprojectinalgeriaundergridfaultconditionsusingdfactsdevices
AT kameldjameleddinekerrouche feasibilitystudyofwindfarmgridconnectedprojectinalgeriaundergridfaultconditionsusingdfactsdevices
AT abdelkadermezouar feasibilitystudyofwindfarmgridconnectedprojectinalgeriaundergridfaultconditionsusingdfactsdevices
AT alexvandenbossche feasibilitystudyofwindfarmgridconnectedprojectinalgeriaundergridfaultconditionsusingdfactsdevices
AT azzedinedraou feasibilitystudyofwindfarmgridconnectedprojectinalgeriaundergridfaultconditionsusingdfactsdevices
AT larbiboumediene feasibilitystudyofwindfarmgridconnectedprojectinalgeriaundergridfaultconditionsusingdfactsdevices