First commissioning of the SuperKEKB vacuum system
The first (Phase-1) commissioning of SuperKEKB, an asymmetric-energy electron-positron collider at KEK, began in February 2016, after more than five years of upgradation work on KEKB and successfully ended in June 2016. A major task of the Phase-1 commissioning was the vacuum scrubbing of new beam p...
| Published in: | Physical Review Accelerators and Beams |
|---|---|
| Main Authors: | , , , , , , |
| Format: | Article |
| Language: | English |
| Published: |
American Physical Society
2016-12-01
|
| Online Access: | http://doi.org/10.1103/PhysRevAccelBeams.19.121001 |