Productivity Models for Operational Planning of Timber Forwarding in Croatia

In the area of Croatian lowland forests, forwarders are usually used for extraction of timber assortments. Within the project »Systematization of norms for the production of timber assortments«, which was financed by the state company »Hrvatske šume« d.o.o. (»Croatian Forests« LLC), the process of d...

Full description

Bibliographic Details
Main Authors: Igor Stankić, Tomislav Poršinsky, Željko Tomašić, Ivica Tonković, Marko Frntić
Format: Article
Language:English
Published: University of Zagreb, Faculty of Forestry 2012-01-01
Series:Croatian Journal of Forest Engineering
Online Access:https://hrcak.srce.hr/file/128026
id doaj-38108c0c627543ef9d638052723bbd26
record_format Article
spelling doaj-38108c0c627543ef9d638052723bbd262020-11-25T02:39:24ZengUniversity of Zagreb, Faculty of ForestryCroatian Journal of Forest Engineering1845-57191848-96722012-01-01331617886030Productivity Models for Operational Planning of Timber Forwarding in CroatiaIgor Stankić0Tomislav Poršinsky1Željko Tomašić2Ivica Tonković3Marko Frntić4Forestry Faculty, University of Zagreb, CroatiaForestry Faculty, University of Zagreb, CroatiaCroatian Forests LLC, Directorate, Zagreb, CroatiaCroatian Forests LLC, Directorate, Zagreb, CroatiaCroatian Forests LLC, Directorate, Zagreb, CroatiaIn the area of Croatian lowland forests, forwarders are usually used for extraction of timber assortments. Within the project »Systematization of norms for the production of timber assortments«, which was financed by the state company »Hrvatske šume« d.o.o. (»Croatian Forests« LLC), the process of development and implementation of new productivity norms for forwarders was carried out. Initially, for the execution of the research, it was necessary to gather data about technical characteristics of forwarders most frequently used in Croatia, but also around the world. The morphological analysis was performed and it was the basis for the classification of forwarders into classes. Three classes of forwarders were obtained after cluster analysis and load capacity appeared to be the most important factor. Machine performance was evaluated on 30 research sites. The standard method of time study (snap-back chronometric technique) was used. During the recording process, data of factors influencing forwarding (stand and terrain conditions) were collected. After analyzing the collected data, it was determined that the forwarding productivity depends on the forwarder class, average extraction distance, load characteristics, terrain and stand conditions. Regression analysis was used for identifying the time consumption of individual work components, and the productivity model for forwarding was developed. The obtained model was implemented into the application HsPPI. This is a part of the information system developed by IT Department of the state enterprise »Hrvatske šume« d.o.o. and is used for production planning in timber harvesting. The system is based on dBase IV databases and two main program modules. The main parts of the system are: tree marking data, assortment structure plan, production plan (felling, processing and extraction) and sales plan. Within a part of the production plan there is a module for calculating productivity norms for timber forwarding.https://hrcak.srce.hr/file/128026
collection DOAJ
language English
format Article
sources DOAJ
author Igor Stankić
Tomislav Poršinsky
Željko Tomašić
Ivica Tonković
Marko Frntić
spellingShingle Igor Stankić
Tomislav Poršinsky
Željko Tomašić
Ivica Tonković
Marko Frntić
Productivity Models for Operational Planning of Timber Forwarding in Croatia
Croatian Journal of Forest Engineering
author_facet Igor Stankić
Tomislav Poršinsky
Željko Tomašić
Ivica Tonković
Marko Frntić
author_sort Igor Stankić
title Productivity Models for Operational Planning of Timber Forwarding in Croatia
title_short Productivity Models for Operational Planning of Timber Forwarding in Croatia
title_full Productivity Models for Operational Planning of Timber Forwarding in Croatia
title_fullStr Productivity Models for Operational Planning of Timber Forwarding in Croatia
title_full_unstemmed Productivity Models for Operational Planning of Timber Forwarding in Croatia
title_sort productivity models for operational planning of timber forwarding in croatia
publisher University of Zagreb, Faculty of Forestry
series Croatian Journal of Forest Engineering
issn 1845-5719
1848-9672
publishDate 2012-01-01
description In the area of Croatian lowland forests, forwarders are usually used for extraction of timber assortments. Within the project »Systematization of norms for the production of timber assortments«, which was financed by the state company »Hrvatske šume« d.o.o. (»Croatian Forests« LLC), the process of development and implementation of new productivity norms for forwarders was carried out. Initially, for the execution of the research, it was necessary to gather data about technical characteristics of forwarders most frequently used in Croatia, but also around the world. The morphological analysis was performed and it was the basis for the classification of forwarders into classes. Three classes of forwarders were obtained after cluster analysis and load capacity appeared to be the most important factor. Machine performance was evaluated on 30 research sites. The standard method of time study (snap-back chronometric technique) was used. During the recording process, data of factors influencing forwarding (stand and terrain conditions) were collected. After analyzing the collected data, it was determined that the forwarding productivity depends on the forwarder class, average extraction distance, load characteristics, terrain and stand conditions. Regression analysis was used for identifying the time consumption of individual work components, and the productivity model for forwarding was developed. The obtained model was implemented into the application HsPPI. This is a part of the information system developed by IT Department of the state enterprise »Hrvatske šume« d.o.o. and is used for production planning in timber harvesting. The system is based on dBase IV databases and two main program modules. The main parts of the system are: tree marking data, assortment structure plan, production plan (felling, processing and extraction) and sales plan. Within a part of the production plan there is a module for calculating productivity norms for timber forwarding.
url https://hrcak.srce.hr/file/128026
work_keys_str_mv AT igorstankic productivitymodelsforoperationalplanningoftimberforwardingincroatia
AT tomislavporsinsky productivitymodelsforoperationalplanningoftimberforwardingincroatia
AT zeljkotomasic productivitymodelsforoperationalplanningoftimberforwardingincroatia
AT ivicatonkovic productivitymodelsforoperationalplanningoftimberforwardingincroatia
AT markofrntic productivitymodelsforoperationalplanningoftimberforwardingincroatia
_version_ 1724786383442149376