Do Projects really end late? On the shortcomings of the classical scheduling techniques

Many engineering projects fail to meet their planned completion dates in real practice. This a recurrent topic in the project management literature, with poor planning and controlling practices frequently cited among the most significant causes of delays. Unfortunately, hardly any attention has been...

Full description

Bibliographic Details
Main Authors: Pablo Ballesteros-Pérez, Graeme D. Larsen, Maria C. González-Cruz
Format: Article
Language:English
Published: OmniaScience 2018-03-01
Series:Journal of Technology and Science Education
Subjects:
Online Access:http://www.jotse.org/index.php/jotse/article/view/303
id doaj-acc0118c63434d0e8e8618127a44c1d6
record_format Article
spelling doaj-acc0118c63434d0e8e8618127a44c1d62020-11-24T22:31:29ZengOmniaScienceJournal of Technology and Science Education2013-63742018-03-0181173310.3926/jotse.303139Do Projects really end late? On the shortcomings of the classical scheduling techniquesPablo Ballesteros-Pérez0Graeme D. Larsen1Maria C. González-Cruz2School of Architecture, Building and Civil Engineering Loughborough University Loughborough, Leicestershire LE11 3TUSchool of the Built Environment. University of Reading. Whiteknights campus, Reading RG6 6DFDepto. de Proyectos de Ingeniería. E.T.S.I. Industriales. Universitat Politècnica de València. Camino de Vera s/n, 46022 ValenciaMany engineering projects fail to meet their planned completion dates in real practice. This a recurrent topic in the project management literature, with poor planning and controlling practices frequently cited among the most significant causes of delays. Unfortunately, hardly any attention has been paid to the fact that the classical scheduling techniques: Gantt chart, Critical Path Method (CPM), and Program Evaluation and Review Technique (PERT), may not be as fit for purpose as they seem. Arguably, because of their relative simplicity, these techniques are still almost the only ones taught nowadays in most introductory courses to scheduling in many engineering and management degrees. However, by utterly ignoring or inappropriately dealing with activity duration variability, these techniques provide optimistic completion dates, while suffering from other shortcomings. Through a series of simple case studies that can be developed with a few participants and common dice, a systematic critique of the classical scheduling techniques is offered. Discussion of the case studies results illustrate why limiting the contents of scheduling education and teaching can be detrimental, as the aforementioned classical scheduling techniques cannot not provide project managers with sufficient resources to effectively plan and control real projects.http://www.jotse.org/index.php/jotse/article/view/303Learning, education
collection DOAJ
language English
format Article
sources DOAJ
author Pablo Ballesteros-Pérez
Graeme D. Larsen
Maria C. González-Cruz
spellingShingle Pablo Ballesteros-Pérez
Graeme D. Larsen
Maria C. González-Cruz
Do Projects really end late? On the shortcomings of the classical scheduling techniques
Journal of Technology and Science Education
Learning, education
author_facet Pablo Ballesteros-Pérez
Graeme D. Larsen
Maria C. González-Cruz
author_sort Pablo Ballesteros-Pérez
title Do Projects really end late? On the shortcomings of the classical scheduling techniques
title_short Do Projects really end late? On the shortcomings of the classical scheduling techniques
title_full Do Projects really end late? On the shortcomings of the classical scheduling techniques
title_fullStr Do Projects really end late? On the shortcomings of the classical scheduling techniques
title_full_unstemmed Do Projects really end late? On the shortcomings of the classical scheduling techniques
title_sort do projects really end late? on the shortcomings of the classical scheduling techniques
publisher OmniaScience
series Journal of Technology and Science Education
issn 2013-6374
publishDate 2018-03-01
description Many engineering projects fail to meet their planned completion dates in real practice. This a recurrent topic in the project management literature, with poor planning and controlling practices frequently cited among the most significant causes of delays. Unfortunately, hardly any attention has been paid to the fact that the classical scheduling techniques: Gantt chart, Critical Path Method (CPM), and Program Evaluation and Review Technique (PERT), may not be as fit for purpose as they seem. Arguably, because of their relative simplicity, these techniques are still almost the only ones taught nowadays in most introductory courses to scheduling in many engineering and management degrees. However, by utterly ignoring or inappropriately dealing with activity duration variability, these techniques provide optimistic completion dates, while suffering from other shortcomings. Through a series of simple case studies that can be developed with a few participants and common dice, a systematic critique of the classical scheduling techniques is offered. Discussion of the case studies results illustrate why limiting the contents of scheduling education and teaching can be detrimental, as the aforementioned classical scheduling techniques cannot not provide project managers with sufficient resources to effectively plan and control real projects.
topic Learning, education
url http://www.jotse.org/index.php/jotse/article/view/303
work_keys_str_mv AT pabloballesterosperez doprojectsreallyendlateontheshortcomingsoftheclassicalschedulingtechniques
AT graemedlarsen doprojectsreallyendlateontheshortcomingsoftheclassicalschedulingtechniques
AT mariacgonzalezcruz doprojectsreallyendlateontheshortcomingsoftheclassicalschedulingtechniques
_version_ 1725736984100470784