The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem

This paper presents the formulation and solution of the Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem. The focus of the proposed method is not on finding a single optimal solution, instead on presenting multiple feasible solutions, with cost and duration information...

Full description

Bibliographic Details
Main Authors: Denis Pinha, Rashpal Ahluwalia, Pedro Senna
Format: Article
Language:English
Published: Kharazmi University 2016-11-01
Series:International Journal of Supply and Operations Management
Subjects:
Online Access:http://www.ijsom.com/article_2707_1a55769b9264de00d8f84eb6bc21977d.pdf
id doaj-b4325b8edccb4fed92deae2454b9ef8f
record_format Article
spelling doaj-b4325b8edccb4fed92deae2454b9ef8f2021-09-29T04:14:36ZengKharazmi UniversityInternational Journal of Supply and Operations Management2383-13592383-25252016-11-01331391141210.22034/2016.3.032707The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling ProblemDenis Pinha0Rashpal Ahluwalia1Pedro Senna2West Virginia University, Morgantown, WV, USAWest Virginia University, Morgantown, WV, USAFederal Center for Technological Education of Rio de Janeiro, Rio de Janeiro, BrazilThis paper presents the formulation and solution of the Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem. The focus of the proposed method is not on finding a single optimal solution, instead on presenting multiple feasible solutions, with cost and duration information to the project manager. The motivation for developing such an approach is due in part to practical situations where the definition of optimal changes on a regular basis. The proposed approach empowers the project manager to determine what is optimal, on a given day, under the current constraints, such as, change of priorities, lack of skilled worker. The proposed method utilizes a simulation approach to determine feasible solutions, under the current constraints. Resources can be non-consumable, consumable, or doubly constrained. The paper also presents a real-life case study dealing with scheduling of ship repair activities.http://www.ijsom.com/article_2707_1a55769b9264de00d8f84eb6bc21977d.pdfresource constrained project schedulingmathematical formulationdiscrete event simulationdecision support system
collection DOAJ
language English
format Article
sources DOAJ
author Denis Pinha
Rashpal Ahluwalia
Pedro Senna
spellingShingle Denis Pinha
Rashpal Ahluwalia
Pedro Senna
The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem
International Journal of Supply and Operations Management
resource constrained project scheduling
mathematical formulation
discrete event simulation
decision support system
author_facet Denis Pinha
Rashpal Ahluwalia
Pedro Senna
author_sort Denis Pinha
title The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem
title_short The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem
title_full The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem
title_fullStr The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem
title_full_unstemmed The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem
title_sort combinatorial multi-mode resource constrained multi-project scheduling problem
publisher Kharazmi University
series International Journal of Supply and Operations Management
issn 2383-1359
2383-2525
publishDate 2016-11-01
description This paper presents the formulation and solution of the Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem. The focus of the proposed method is not on finding a single optimal solution, instead on presenting multiple feasible solutions, with cost and duration information to the project manager. The motivation for developing such an approach is due in part to practical situations where the definition of optimal changes on a regular basis. The proposed approach empowers the project manager to determine what is optimal, on a given day, under the current constraints, such as, change of priorities, lack of skilled worker. The proposed method utilizes a simulation approach to determine feasible solutions, under the current constraints. Resources can be non-consumable, consumable, or doubly constrained. The paper also presents a real-life case study dealing with scheduling of ship repair activities.
topic resource constrained project scheduling
mathematical formulation
discrete event simulation
decision support system
url http://www.ijsom.com/article_2707_1a55769b9264de00d8f84eb6bc21977d.pdf
work_keys_str_mv AT denispinha thecombinatorialmultimoderesourceconstrainedmultiprojectschedulingproblem
AT rashpalahluwalia thecombinatorialmultimoderesourceconstrainedmultiprojectschedulingproblem
AT pedrosenna thecombinatorialmultimoderesourceconstrainedmultiprojectschedulingproblem
AT denispinha combinatorialmultimoderesourceconstrainedmultiprojectschedulingproblem
AT rashpalahluwalia combinatorialmultimoderesourceconstrainedmultiprojectschedulingproblem
AT pedrosenna combinatorialmultimoderesourceconstrainedmultiprojectschedulingproblem
_version_ 1716864964467097600