A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect Manufacturing

Nowadays, the manufacturing industry is constantly changing. Production systems must operate in a highly dynamic environment where unexpected events could occur and create disruption, making rescheduling inevitable for manufacturing companies. Rescheduling models are fundamental to the robustness of...

Full description

Bibliographic Details
Main Authors: Foivos Psarommatis, Giacomo Martiriggiano, Xiaochen Zheng, Dimitris Kiritsis
Format: Article
Language:English
Published: Frontiers Media S.A. 2021-04-01
Series:Frontiers in Mechanical Engineering
Subjects:
Online Access:https://www.frontiersin.org/articles/10.3389/fmech.2021.646507/full
id doaj-c452b34ef07540b69ed159a50c1c416b
record_format Article
spelling doaj-c452b34ef07540b69ed159a50c1c416b2021-04-26T07:49:33ZengFrontiers Media S.A.Frontiers in Mechanical Engineering2297-30792021-04-01710.3389/fmech.2021.646507646507A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect ManufacturingFoivos PsarommatisGiacomo MartiriggianoXiaochen ZhengDimitris KiritsisNowadays, the manufacturing industry is constantly changing. Production systems must operate in a highly dynamic environment where unexpected events could occur and create disruption, making rescheduling inevitable for manufacturing companies. Rescheduling models are fundamental to the robustness of production processes. This paper proposes a model to address rescheduling caused by unexpected events, aiming to achieve the zero-defect manufacturing (ZDM) concept. The goal of the model is to incorporate traditional and ZDM–oriented events into one methodology to calculate when the next rescheduling will be performed to effectively react to unexpected events. The methodology relies on the definition of two key time parameters for each event type: event response time (RT) and event delay response time (DRT). Based on these parameters, an event management algorithm is designed to identify the optimal rescheduling solution. The DRT parameter is calculated based on a multi-parametric dynamic formula to capture the dynamics of production. Moreover, ANOM, and ANOVA methods are used to analyse the behaviour of the developed method and to assess the level of robustness of the proposed approach. Finally, a case study based on real production scenarios is conducted, a series of simulation experiments are performed, and comparisons with other rescheduling policies are presented. The results demonstrate the effectiveness of the proposed event management algorithm for managing rescheduling.https://www.frontiersin.org/articles/10.3389/fmech.2021.646507/fullzero-defect manufacturingreschedulingunexpected eventsevents managementdesign of experiments
collection DOAJ
language English
format Article
sources DOAJ
author Foivos Psarommatis
Giacomo Martiriggiano
Xiaochen Zheng
Dimitris Kiritsis
spellingShingle Foivos Psarommatis
Giacomo Martiriggiano
Xiaochen Zheng
Dimitris Kiritsis
A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect Manufacturing
Frontiers in Mechanical Engineering
zero-defect manufacturing
rescheduling
unexpected events
events management
design of experiments
author_facet Foivos Psarommatis
Giacomo Martiriggiano
Xiaochen Zheng
Dimitris Kiritsis
author_sort Foivos Psarommatis
title A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect Manufacturing
title_short A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect Manufacturing
title_full A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect Manufacturing
title_fullStr A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect Manufacturing
title_full_unstemmed A Generic Methodology for Calculating Rescheduling Time for Multiple Unexpected Events in the Era of Zero Defect Manufacturing
title_sort generic methodology for calculating rescheduling time for multiple unexpected events in the era of zero defect manufacturing
publisher Frontiers Media S.A.
series Frontiers in Mechanical Engineering
issn 2297-3079
publishDate 2021-04-01
description Nowadays, the manufacturing industry is constantly changing. Production systems must operate in a highly dynamic environment where unexpected events could occur and create disruption, making rescheduling inevitable for manufacturing companies. Rescheduling models are fundamental to the robustness of production processes. This paper proposes a model to address rescheduling caused by unexpected events, aiming to achieve the zero-defect manufacturing (ZDM) concept. The goal of the model is to incorporate traditional and ZDM–oriented events into one methodology to calculate when the next rescheduling will be performed to effectively react to unexpected events. The methodology relies on the definition of two key time parameters for each event type: event response time (RT) and event delay response time (DRT). Based on these parameters, an event management algorithm is designed to identify the optimal rescheduling solution. The DRT parameter is calculated based on a multi-parametric dynamic formula to capture the dynamics of production. Moreover, ANOM, and ANOVA methods are used to analyse the behaviour of the developed method and to assess the level of robustness of the proposed approach. Finally, a case study based on real production scenarios is conducted, a series of simulation experiments are performed, and comparisons with other rescheduling policies are presented. The results demonstrate the effectiveness of the proposed event management algorithm for managing rescheduling.
topic zero-defect manufacturing
rescheduling
unexpected events
events management
design of experiments
url https://www.frontiersin.org/articles/10.3389/fmech.2021.646507/full
work_keys_str_mv AT foivospsarommatis agenericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
AT giacomomartiriggiano agenericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
AT xiaochenzheng agenericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
AT dimitriskiritsis agenericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
AT foivospsarommatis genericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
AT giacomomartiriggiano genericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
AT xiaochenzheng genericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
AT dimitriskiritsis genericmethodologyforcalculatingreschedulingtimeformultipleunexpectedeventsintheeraofzerodefectmanufacturing
_version_ 1721507732621623296