PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPAN
Abstract In this study done on leather shoe company that uses flow shop scheduling strategies. Where the purpose of this study is to minimize makespan is the total time needed to complete the entire job. This is done because of the large demand for leather shoes that exceeds the production capacity...
Main Authors: | , , |
---|---|
Format: | Article |
Language: | English |
Published: |
University of Brawijaya
2015-03-01
|
Series: | Journal of Engineering and Management in Industrial System |
Subjects: | |
Online Access: | https://jemis.ub.ac.id/index.php/jemis/article/view/152 |
id |
doaj-ea0a41bfcdd946cb9a31e743890582e7 |
---|---|
record_format |
Article |
spelling |
doaj-ea0a41bfcdd946cb9a31e743890582e72020-11-25T01:27:28ZengUniversity of BrawijayaJournal of Engineering and Management in Industrial System2338-39252477-60252015-03-013110.21776/ub.jemis.2015.003.01.6140PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPANHasan Bashori0Pratikto Pratikto1Sugiono Sugiono2Universitas BrawijayaUniversitas BrawijayaUniversitas BrawijayaAbstract In this study done on leather shoe company that uses flow shop scheduling strategies. Where the purpose of this study is to minimize makespan is the total time needed to complete the entire job. This is done because of the large demand for leather shoes that exceeds the production capacity and production scheduling by the company based on intuition. In solving the production scheduling problem that occurs in the company, Cross Entropy algorithm used method-Genetic Algorithm (CEGA) to minimize the makespan. From the results of calculations with CEGA method sequences obtained by scheduling makespan value of 5822 seconds with an efficiency of 6.79% when compared with the method of the company with sebasar makespan value of 6246 seconds.https://jemis.ub.ac.id/index.php/jemis/article/view/152Cross Entropy Algorithm-Genetic Algorithm (CEGA)Flow Shop SchedulingMakespan Minimization |
collection |
DOAJ |
language |
English |
format |
Article |
sources |
DOAJ |
author |
Hasan Bashori Pratikto Pratikto Sugiono Sugiono |
spellingShingle |
Hasan Bashori Pratikto Pratikto Sugiono Sugiono PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPAN Journal of Engineering and Management in Industrial System Cross Entropy Algorithm-Genetic Algorithm (CEGA) Flow Shop Scheduling Makespan Minimization |
author_facet |
Hasan Bashori Pratikto Pratikto Sugiono Sugiono |
author_sort |
Hasan Bashori |
title |
PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPAN |
title_short |
PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPAN |
title_full |
PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPAN |
title_fullStr |
PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPAN |
title_full_unstemmed |
PENJADWALAN FLOW SHOP DENGAN PENERAPAN CROSS ENTROPY-GENETIC ALGORITHM (CEGA) UNTUK MEMINIMASI MAKESPAN |
title_sort |
penjadwalan flow shop dengan penerapan cross entropy-genetic algorithm (cega) untuk meminimasi makespan |
publisher |
University of Brawijaya |
series |
Journal of Engineering and Management in Industrial System |
issn |
2338-3925 2477-6025 |
publishDate |
2015-03-01 |
description |
Abstract In this study done on leather shoe company that uses flow shop scheduling strategies. Where the purpose of this study is to minimize makespan is the total time needed to complete the entire job. This is done because of the large demand for leather shoes that exceeds the production capacity and production scheduling by the company based on intuition. In solving the production scheduling problem that occurs in the company, Cross Entropy algorithm used method-Genetic Algorithm (CEGA) to minimize the makespan. From the results of calculations with CEGA method sequences obtained by scheduling makespan value of 5822 seconds with an efficiency of 6.79% when compared with the method of the company with sebasar makespan value of 6246 seconds. |
topic |
Cross Entropy Algorithm-Genetic Algorithm (CEGA) Flow Shop Scheduling Makespan Minimization |
url |
https://jemis.ub.ac.id/index.php/jemis/article/view/152 |
work_keys_str_mv |
AT hasanbashori penjadwalanflowshopdenganpenerapancrossentropygeneticalgorithmcegauntukmeminimasimakespan AT pratiktopratikto penjadwalanflowshopdenganpenerapancrossentropygeneticalgorithmcegauntukmeminimasimakespan AT sugionosugiono penjadwalanflowshopdenganpenerapancrossentropygeneticalgorithmcegauntukmeminimasimakespan |
_version_ |
1725105275151581184 |