Identification of Schedule-Performance Indicators and Delay-Recovery Strategies for Low-Cost Housing Projects

Many construction projects suffer from schedule delays that ultimately lead to considerable cost overruns and defeat the purpose of low-cost housing (LCH), which is to support low-income earners. It is, therefore, vital that the schedule delays and cost overruns be minimized. The objectives of this...

Full description

Bibliographic Details
Main Authors: Elnaz Safapour, Sharareh Kermanshachi, Bahaa Alfasi, Reza Akhavian
Format: Article
Language:English
Published: MDPI AG 2019-10-01
Series:Sustainability
Subjects:
Online Access:https://www.mdpi.com/2071-1050/11/21/6005
Description
Summary:Many construction projects suffer from schedule delays that ultimately lead to considerable cost overruns and defeat the purpose of low-cost housing (LCH), which is to support low-income earners. It is, therefore, vital that the schedule delays and cost overruns be minimized. The objectives of this research were to investigate, identify, and classify the schedule-delay indicators (SDIs), prioritize them based on their level of impact, and formulate constructive strategies to improve the schedule performance. To achieve the objectives set forth, 68 interviews were conducted with professionals who are active in LCH projects, and a structured survey was developed and distributed to other experts involved in LCH projects to validate the result of the interviews and collect additional data. Survey responses were collected from 101 individuals and were analyzed. The significant SDIs were identified and classified by the research team and were ranked and prioritized, using the Relative Importance Index (RII) method. The results demonstrated that the identified SDIs could be classified into the following eight main categories: legal, design and technology, project characteristic, project management, material resource, human resource, location, and finance. The outcomes of this study will help project managers and stakeholders identify the causes of schedule delays early in the project and implement effective strategies for improving project performance in low-cost housing projects.