Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1

碩士 === 朝陽科技大學 === 營建工程系碩士班 === 96 === After the amendment, the Paragraph 2, Article 85-1 of Government Procurement Act provided that the construction dispute shall be settled through the mechanism of mediation and arbitration in sequence (what is called “Med-Arb”). In the past, the authority hadn’t...

Full description

Bibliographic Details
Main Authors: Ben-Yuan Hung, 洪本原
Other Authors: Sheng-Min Wu
Format: Others
Language:zh-TW
Published: 2008
Online Access:http://ndltd.ncl.edu.tw/handle/27252044405676839197
id ndltd-TW-096CYUT5582024
record_format oai_dc
spelling ndltd-TW-096CYUT55820242015-11-27T04:04:14Z http://ndltd.ncl.edu.tw/handle/27252044405676839197 Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1 政府採購法第八十五條之一修訂對工程爭議處理實務之影響 Ben-Yuan Hung 洪本原 碩士 朝陽科技大學 營建工程系碩士班 96 After the amendment, the Paragraph 2, Article 85-1 of Government Procurement Act provided that the construction dispute shall be settled through the mechanism of mediation and arbitration in sequence (what is called “Med-Arb”). In the past, the authority hadn’t belief and was also unwilling to arbitrate because of arbitrator agentization, unfair arbitration awards, and excessively severe conditions for the revocation of arbitration awards. In the process of conclusion of the mediation, it is necessary for both parties to make an agreement and concession. However, the public servants are afraid of being fallen into a profit-making swamp so that they will more like to avoid agreeing to accept the mediation suggestion. In practical cases, the contractor cannot look for further relief according to the Article 85-1 of the Government Procurement Act as amended because the authority takes uncompromising attitudes in itself and the mediation committee is unwilling to make a mediation suggestion or project due to too-big differences between both parties. Besides, if the contractor regarded the mediation as a tool of entering the arbitration process, dealt with the other party courteously but without sincerity in the mediation process only in search of a mediation suggestion or project, and devoted every effort to follow-up arbitration based on the Procurement Act as amended, then it is unavoidable to have a doubtful point of “Insincerely Playing a Part in Mediation but Actually Seek an Arbitration”. With the data collection, this paper analyzes and studies such documentary contents as various theories and empirical cases. In order to dissect the problems faced by the “Med-Arb” system, we will not only understand its applicable scope and the doubtful point resulted from its implementation but also analyze & study the status or position of the public servants in the authority. For the result, this research provides the analysis of three essential elements for the “Med-Arb” system and also suggests both of the authority and the contractor shall take positive and active attitudes toward this system to avoid the mediation system from being toolized and distorted. This paper suggests to modify the Regulations Governing the Mediation for Dispute Regarding the Performance of the Contract for Government Procurement to provide a supporting measure for the Med-Arb system to the legislation institution and other organizations for their references, making the “Med-Arb” system be broadly trusted and accepted in conformity with the intention of Article 85-1 of the Government Procurement Act as amended. Sheng-Min Wu 伍勝民 2008 學位論文 ; thesis 161 zh-TW
collection NDLTD
language zh-TW
format Others
sources NDLTD
description 碩士 === 朝陽科技大學 === 營建工程系碩士班 === 96 === After the amendment, the Paragraph 2, Article 85-1 of Government Procurement Act provided that the construction dispute shall be settled through the mechanism of mediation and arbitration in sequence (what is called “Med-Arb”). In the past, the authority hadn’t belief and was also unwilling to arbitrate because of arbitrator agentization, unfair arbitration awards, and excessively severe conditions for the revocation of arbitration awards. In the process of conclusion of the mediation, it is necessary for both parties to make an agreement and concession. However, the public servants are afraid of being fallen into a profit-making swamp so that they will more like to avoid agreeing to accept the mediation suggestion. In practical cases, the contractor cannot look for further relief according to the Article 85-1 of the Government Procurement Act as amended because the authority takes uncompromising attitudes in itself and the mediation committee is unwilling to make a mediation suggestion or project due to too-big differences between both parties. Besides, if the contractor regarded the mediation as a tool of entering the arbitration process, dealt with the other party courteously but without sincerity in the mediation process only in search of a mediation suggestion or project, and devoted every effort to follow-up arbitration based on the Procurement Act as amended, then it is unavoidable to have a doubtful point of “Insincerely Playing a Part in Mediation but Actually Seek an Arbitration”. With the data collection, this paper analyzes and studies such documentary contents as various theories and empirical cases. In order to dissect the problems faced by the “Med-Arb” system, we will not only understand its applicable scope and the doubtful point resulted from its implementation but also analyze & study the status or position of the public servants in the authority. For the result, this research provides the analysis of three essential elements for the “Med-Arb” system and also suggests both of the authority and the contractor shall take positive and active attitudes toward this system to avoid the mediation system from being toolized and distorted. This paper suggests to modify the Regulations Governing the Mediation for Dispute Regarding the Performance of the Contract for Government Procurement to provide a supporting measure for the Med-Arb system to the legislation institution and other organizations for their references, making the “Med-Arb” system be broadly trusted and accepted in conformity with the intention of Article 85-1 of the Government Procurement Act as amended.
author2 Sheng-Min Wu
author_facet Sheng-Min Wu
Ben-Yuan Hung
洪本原
author Ben-Yuan Hung
洪本原
spellingShingle Ben-Yuan Hung
洪本原
Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1
author_sort Ben-Yuan Hung
title Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1
title_short Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1
title_full Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1
title_fullStr Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1
title_full_unstemmed Effects of Dispute Resolution Due to Amendment of Government Procurement Act Article 85-1
title_sort effects of dispute resolution due to amendment of government procurement act article 85-1
publishDate 2008
url http://ndltd.ncl.edu.tw/handle/27252044405676839197
work_keys_str_mv AT benyuanhung effectsofdisputeresolutionduetoamendmentofgovernmentprocurementactarticle851
AT hóngběnyuán effectsofdisputeresolutionduetoamendmentofgovernmentprocurementactarticle851
AT benyuanhung zhèngfǔcǎigòufǎdìbāshíwǔtiáozhīyīxiūdìngduìgōngchéngzhēngyìchùlǐshíwùzhīyǐngxiǎng
AT hóngběnyuán zhèngfǔcǎigòufǎdìbāshíwǔtiáozhīyīxiūdìngduìgōngchéngzhēngyìchùlǐshíwùzhīyǐngxiǎng
_version_ 1718137325914947584