The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils

碩士 === 國立屏東科技大學 === 土木工程系所 === 97 === The objective of the study is to investigate the encountered problems and associated remediation for the installation of jacking pipes within the gravelly soils in Taiwan. The study areas included the major cities along the west coast sedimentation plain and Hwa...

Full description

Bibliographic Details
Main Authors: Young-Chin Kuo, 郭永進
Other Authors: Chiwan Hsieh
Format: Others
Language:zh-TW
Online Access:http://ndltd.ncl.edu.tw/handle/83358710606813568512
id ndltd-TW-097NPUS5015005
record_format oai_dc
spelling ndltd-TW-097NPUS50150052016-12-22T04:11:42Z http://ndltd.ncl.edu.tw/handle/83358710606813568512 The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils 台灣地區卵礫石層污水下水道管推進工法之施工 Young-Chin Kuo 郭永進 碩士 國立屏東科技大學 土木工程系所 97 The objective of the study is to investigate the encountered problems and associated remediation for the installation of jacking pipes within the gravelly soils in Taiwan. The study areas included the major cities along the west coast sedimentation plain and Hwa-Tung village. On-site interview with the on-site engineering directors to collect construction details for ten pipe jacking projects within gravelly soils were conducted. The collection information was further analyzed and evaluated. The installation methods, jacking machine specifications, encountered problems and remediation procedure were also investigated. Based upon the analyses, practical suggestions for installation and selection of jacking pipe equipments are also recommended to the engineers for the future pipe jacking projects in gravelly soils. The depth of subsurface investigation should be minimum 3 meters below the deepest elevation of the jacking pipes. A test pit with 1 to 2 meters in width and 2 to 3 meter in depth should be excavated to explore the subsurface condition of the project site. 40%, 20%, and less than 20% opening at cutter head is recommended for pipe jacking machine equal or over 500 mm, 400 mm, and 300 mm, in diameter, respectively. It is recommended that a minimum of 500 mm pipe jacking machine should be used as encountered gravelly soil in Taiwan. Some modifications were necessary for the imported pipe jacking equipments for use in Taiwan gravelly soils. 40% cutter head opening was commonly used for earth-pressure balance drilling machine. 15% to 40% opening was typically used for Soil-slurry balance jacking machine. A minimum of 12,000 kg/cm2 jacking pressure should be used as encountered gravelly soils. When encountered silty and sandy soils, it is recommended to increase drilling pressure, modify the compound of slurry fluid, and reinforce the drainage pipes to eliminate construction problems. Chiwan Hsieh 謝啟萬 學位論文 ; thesis 118 zh-TW
collection NDLTD
language zh-TW
format Others
sources NDLTD
description 碩士 === 國立屏東科技大學 === 土木工程系所 === 97 === The objective of the study is to investigate the encountered problems and associated remediation for the installation of jacking pipes within the gravelly soils in Taiwan. The study areas included the major cities along the west coast sedimentation plain and Hwa-Tung village. On-site interview with the on-site engineering directors to collect construction details for ten pipe jacking projects within gravelly soils were conducted. The collection information was further analyzed and evaluated. The installation methods, jacking machine specifications, encountered problems and remediation procedure were also investigated. Based upon the analyses, practical suggestions for installation and selection of jacking pipe equipments are also recommended to the engineers for the future pipe jacking projects in gravelly soils. The depth of subsurface investigation should be minimum 3 meters below the deepest elevation of the jacking pipes. A test pit with 1 to 2 meters in width and 2 to 3 meter in depth should be excavated to explore the subsurface condition of the project site. 40%, 20%, and less than 20% opening at cutter head is recommended for pipe jacking machine equal or over 500 mm, 400 mm, and 300 mm, in diameter, respectively. It is recommended that a minimum of 500 mm pipe jacking machine should be used as encountered gravelly soil in Taiwan. Some modifications were necessary for the imported pipe jacking equipments for use in Taiwan gravelly soils. 40% cutter head opening was commonly used for earth-pressure balance drilling machine. 15% to 40% opening was typically used for Soil-slurry balance jacking machine. A minimum of 12,000 kg/cm2 jacking pressure should be used as encountered gravelly soils. When encountered silty and sandy soils, it is recommended to increase drilling pressure, modify the compound of slurry fluid, and reinforce the drainage pipes to eliminate construction problems.
author2 Chiwan Hsieh
author_facet Chiwan Hsieh
Young-Chin Kuo
郭永進
author Young-Chin Kuo
郭永進
spellingShingle Young-Chin Kuo
郭永進
The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils
author_sort Young-Chin Kuo
title The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils
title_short The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils
title_full The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils
title_fullStr The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils
title_full_unstemmed The Installation of Sewer Pipe Lines using Jacking Pipe Methods in Taiwan Gravelly Soils
title_sort installation of sewer pipe lines using jacking pipe methods in taiwan gravelly soils
url http://ndltd.ncl.edu.tw/handle/83358710606813568512
work_keys_str_mv AT youngchinkuo theinstallationofsewerpipelinesusingjackingpipemethodsintaiwangravellysoils
AT guōyǒngjìn theinstallationofsewerpipelinesusingjackingpipemethodsintaiwangravellysoils
AT youngchinkuo táiwāndeqūluǎnlìshícéngwūshuǐxiàshuǐdàoguǎntuījìngōngfǎzhīshīgōng
AT guōyǒngjìn táiwāndeqūluǎnlìshícéngwūshuǐxiàshuǐdàoguǎntuījìngōngfǎzhīshīgōng
AT youngchinkuo installationofsewerpipelinesusingjackingpipemethodsintaiwangravellysoils
AT guōyǒngjìn installationofsewerpipelinesusingjackingpipemethodsintaiwangravellysoils
_version_ 1718402595032137728