4D Automatic Scheduling in High-Tech Facility Construction

碩士 === 國立臺灣大學 === 土木工程學研究所 === 104 === High-Tech industry develops rapidly in Taiwan. Due to the highly competitive market and the characteristic of short life-cycles in high-tech semiconductor products, high-tech facility construction must be promoted to adapt the trend. Quality management and sch...

Full description

Bibliographic Details
Main Authors: Che-Wei Hsu, 許哲瑋
Other Authors: Luh-Maan Chang
Format: Others
Language:zh-TW
Published: 2016
Online Access:http://ndltd.ncl.edu.tw/handle/20601488451989230786
id ndltd-TW-104NTU05015070
record_format oai_dc
spelling ndltd-TW-104NTU050150702017-04-29T04:31:56Z http://ndltd.ncl.edu.tw/handle/20601488451989230786 4D Automatic Scheduling in High-Tech Facility Construction 應用4D自動排程於高科技廠房系統設備施工之研究 Che-Wei Hsu 許哲瑋 碩士 國立臺灣大學 土木工程學研究所 104 High-Tech industry develops rapidly in Taiwan. Due to the highly competitive market and the characteristic of short life-cycles in high-tech semiconductor products, high-tech facility construction must be promoted to adapt the trend. Quality management and schedule management become highly focused in a high-tech facility construction project. Building information modeling (BIM) is a tool that has well performance in integrating construction information. As a result, intensifying BIM applications in high-tech facility must have a great improvement in schedule management in construction site. Schedule and 3D CAD are two critical factors in 4D. However, schedule management and 3D CAD are still hard to integrate in current method. Planning construction schedule and drawing 3D CAD are two separated works. As a result, there is a linking process between 3D CAD and schedule. Integrating 3D model and schedule becomes the critical issue to improve the efficiency of 4D. The goal of this research is to develop a BIM-based automatic scheduling method and apply it on high-tech facility construction. The study first exported the information of high-tech facility objects from 3D model. The 4D automatic scheduling program calculated the duration and arranged the sequence of the objects according to the data in Resource Model and Action Model. Then, the program came up with a project schedule under the resource constraint. Project managers could check the result through the 4D faster than before and formulate the strategy. At last, the study used NTUEE 7-5 Nano Lab as a case study to demonstrate the methodology. This study presents a BIM-based automatic scheduling method that employs 3D objects to generate information required for project scheduling to deal with the complexity of high-tech facility construction and assist construction project managers in making appropriate decisions. Luh-Maan Chang 張陸滿 2016 學位論文 ; thesis 81 zh-TW
collection NDLTD
language zh-TW
format Others
sources NDLTD
description 碩士 === 國立臺灣大學 === 土木工程學研究所 === 104 === High-Tech industry develops rapidly in Taiwan. Due to the highly competitive market and the characteristic of short life-cycles in high-tech semiconductor products, high-tech facility construction must be promoted to adapt the trend. Quality management and schedule management become highly focused in a high-tech facility construction project. Building information modeling (BIM) is a tool that has well performance in integrating construction information. As a result, intensifying BIM applications in high-tech facility must have a great improvement in schedule management in construction site. Schedule and 3D CAD are two critical factors in 4D. However, schedule management and 3D CAD are still hard to integrate in current method. Planning construction schedule and drawing 3D CAD are two separated works. As a result, there is a linking process between 3D CAD and schedule. Integrating 3D model and schedule becomes the critical issue to improve the efficiency of 4D. The goal of this research is to develop a BIM-based automatic scheduling method and apply it on high-tech facility construction. The study first exported the information of high-tech facility objects from 3D model. The 4D automatic scheduling program calculated the duration and arranged the sequence of the objects according to the data in Resource Model and Action Model. Then, the program came up with a project schedule under the resource constraint. Project managers could check the result through the 4D faster than before and formulate the strategy. At last, the study used NTUEE 7-5 Nano Lab as a case study to demonstrate the methodology. This study presents a BIM-based automatic scheduling method that employs 3D objects to generate information required for project scheduling to deal with the complexity of high-tech facility construction and assist construction project managers in making appropriate decisions.
author2 Luh-Maan Chang
author_facet Luh-Maan Chang
Che-Wei Hsu
許哲瑋
author Che-Wei Hsu
許哲瑋
spellingShingle Che-Wei Hsu
許哲瑋
4D Automatic Scheduling in High-Tech Facility Construction
author_sort Che-Wei Hsu
title 4D Automatic Scheduling in High-Tech Facility Construction
title_short 4D Automatic Scheduling in High-Tech Facility Construction
title_full 4D Automatic Scheduling in High-Tech Facility Construction
title_fullStr 4D Automatic Scheduling in High-Tech Facility Construction
title_full_unstemmed 4D Automatic Scheduling in High-Tech Facility Construction
title_sort 4d automatic scheduling in high-tech facility construction
publishDate 2016
url http://ndltd.ncl.edu.tw/handle/20601488451989230786
work_keys_str_mv AT cheweihsu 4dautomaticschedulinginhightechfacilityconstruction
AT xǔzhéwěi 4dautomaticschedulinginhightechfacilityconstruction
AT cheweihsu yīngyòng4dzìdòngpáichéngyúgāokējìchǎngfángxìtǒngshèbèishīgōngzhīyánjiū
AT xǔzhéwěi yīngyòng4dzìdòngpáichéngyúgāokējìchǎngfángxìtǒngshèbèishīgōngzhīyánjiū
_version_ 1718445597379264512