An Applicable Heuristic for Scheduling Multi-mode Resource Constraint Projects Using PERT Technique in the Presence of Uncertain Duration of Activities

In project planning process, resource over-allocation is a major shortcoming. The resource over-allocation causes the schedules not to be applicable in practice. Besides, in real projects, it is hard to predict the duration of activities since they may be changed due to lack of resources, delays in...

Full description

Bibliographic Details
Main Authors: Aidin Delgoshaei, Ahad Ali, Masih Parvin, Maryam Ghoreishi
Format: Article
Language:English
Published: Kharazmi University 2018-11-01
Series:International Journal of Supply and Operations Management
Subjects:
Online Access:http://www.ijsom.com/article_2770_984789689bea57af13c5c796a78374f2.pdf