The method for improving stability of construction project schedules through buffer allocation / Statybos vykdymo grafiko stabilumo užtikrinimas paskirstant laiko rezervus

The actual completion time of construction projects is rarely in accordance with initial plans. This is due to unforeseen events that affect the project execution. In the paper, the authors propose a method of improving the construction schedule reliability. The method is based on the idea of buffe...