Rrsearch on Compensation of Project Overhead Damages For Owner Caused Concurrent Delay of Responsibility Apportionment
碩士 === 國立臺灣科技大學 === 營建工程系 === 98 === It is generally recognized that construction delays is critical in public construction projects. Contractors may claim incurred costs for excusable and compensable delays.And it often leads to contract disputes due to the lack of effective settlement approaches.C...